Question 903733: Working 8 hours daily, 40 people can dig the foundation of a building in 21 days. Working for 10 hours daily if the work is to be finished in 14 days, how many people are needed to finish the same work?
This is from the chapter Direct and Inverse proportion for Grade VIII. Cannot seem to get the concept of having 3 variables.
Answer by richwmiller(17219) (Show Source): You can put this solution on YOUR website!
8*40*21=6720 man hours
10*14=140
6720/140=48
48 men needed to do the job in 14 days working 10 hours a day!
RELATED QUESTIONS
Working for 8 hrs daily, 40 men can complete in 21 days. Working for 10 hrs daily, If the (answered by ptaylor)
working 5 hours daily, shashi can embroider 3 saries in 21 days. How long will it take... (answered by josgarithmetic)
15 men plough a land in 14 days working 12 hours daily.How many days will be taken by 21... (answered by josgarithmetic)
15 labourers working 9 hours daily can reap the field in 8 days. find how many workers... (answered by ankor@dixie-net.com)
A manager hires 25 persons to make 100 bicycles working 4 hours daily. How many bicycles... (answered by knighty2002uk)
1.'A' works twice as fast as 'B'. If both of them together take 6 days to complete the... (answered by josmiceli,vvnrichards)
If 12 persons working 12 hours a day dig 12 meter of tunnel in 12 days. How many men are (answered by josmiceli)
30 men repair a road in 56 days by working 6 hours daily. In how many days 45 men will... (answered by stanbon)
10 men working for 6 days of 10 hours each finish 5/21 of a piece of work. How many men... (answered by richwmiller)