SOLUTION: If 12 persons worked 9 hours per day and completed making of 12 toys in 6 days , then find in how many days can 18 persons work 6 hours per day can complete making of 24 toys

Algebra.Com
Question 903499: If 12 persons worked 9 hours per day and completed making of 12 toys in 6 days , then find in how many days can 18 persons work 6 hours per day can complete making of 24 toys
Answer by ankor@dixie-net.com(22740)   (Show Source): You can put this solution on YOUR website!
If 12 persons worked 9 hours per day and completed making of 12 toys in 6 days ,
Find how many man-hrs to make 12 toys
12*9*6 = 648 man-hrs
then find how many man-hrs to make one toy
648/12 = 54 man-hrs per toy
:
then find in how many days can 18 persons work 6 hours per day can complete making of 24 toys
let d = no. of days required to accomplish this
18*6*d = 24*54
108d = 1296
d = 1296/108
d = 12 days

RELATED QUESTIONS

if 10 persos done a job in 18 days then 12 persons done the same job in how many... (answered by josgarithmetic)
If 12 persons working 12 hours a day dig 12 meter of tunnel in 12 days. How many men are (answered by josmiceli)
1.'A' works twice as fast as 'B'. If both of them together take 6 days to complete the... (answered by josmiceli,vvnrichards)
If one sack of rice can be consumed by 3 persons in 36 days, in how many days will 9... (answered by josgarithmetic)
5 men can prepare 10 toys in 6 days working 6 hours a day. In how many days can 12 men... (answered by josgarithmetic,ikleyn)
Please solve this question : two persons A and B together can do work in 10 days. the... (answered by richwmiller)
If the food in the basket is sufficient to feed 10 persons in 12 days, how many days... (answered by josgarithmetic)
15 persons can do the job in 6 days, how many extra persons are required if it would have (answered by nyc_function)
If 1200 persons can finish the construction of a building in 40 days, how many persons... (answered by richwmiller)