Question 901017: agr 84 mens kisi work ko 17days me karte h to usi work ko 119mens kitne days me karenge??
Answer by richwmiller(17219) (Show Source): You can put this solution on YOUR website!
84 men work 17 days
84*17=1428
1428/119=12 days for 119 men
12 days for 119 men
RELATED QUESTIONS
2+6+10+14+18+22+26+30+34+38 ish me se kisi 5 ank ko lekr 100 purana h ???
(answered by Edwin McCravy)
ek tarbuj ko bhar ke anusar 3:5 ke anupat m kata gya.usme bade tukde ko bhar ke anusar... (answered by solver91311)
2 men and 5 women can together complete the work in 4 days while 3 mens and 6 women can... (answered by stanbon)
Ten mens can finish a work in 15days.15womens can finish a same work in 12days. How many... (answered by ptaylor)
somne persons can do a work in 60 days 8 more mens are added them then can do a work in... (answered by josgarithmetic)
if a man completes a work in 9 days,second man complete work in 7 days and 3 mens... (answered by ankor@dixie-net.com)
Find the length of the perpendicular from R to KO when R (3 , 4), K ( 3 , 1) and O ( 8 ,... (answered by lwsshak3)
Factor completely. Show work
x2 - 5x – 84
can some one help me out (answered by Alan3354)
If 6 men can do a piece of work in 14 days, how many men are needed to do the work in 21... (answered by babynarah2007)