SOLUTION: 10 men can complete a job in 14 days.how long will it take 4 men to finish same job if they work at the same rate?
Algebra.Com
Question 898577: 10 men can complete a job in 14 days.how long will it take 4 men to finish same job if they work at the same rate?
Found 2 solutions by josmiceli, josgarithmetic:
Answer by josmiceli(19441) (Show Source): You can put this solution on YOUR website!
10 men complete a job in 14 days
--------------------------------
1 man will take 10 times as long to do the job, so
-------------------------------------------
1 man completes a job in 140 days
----------------------------------------
4 men can complete the job in 1/4 of that time, so
---------------------------------------------
4 men can complete a job in 35 days
Answer by josgarithmetic(39616) (Show Source): You can put this solution on YOUR website!
"if they work at the same rate?" What do you mean?
Try it this way.
Let r = the rate for ONE man, assuming each man works at this rate.
, doing the one job and using the uniform rate idea, RT=J for rate time job. The factor used with the number r is for how many men are doing work, since the rate of any group is the sum of the individual rates, and all of them being r. is the time, unknown, in days for the group of four men.
Just solve for .
RELATED QUESTIONS
10 men can complete a job in 14 days. How long will it take 4 men to finish the same job... (answered by josgarithmetic)
If 20 men can complete a piece of job in 8days, how long will it take 10 men to finish... (answered by Theo)
It takes 4 men 6 hours to repair a road. How long will it take 7 men to do the job if... (answered by lenny460)
Five men take 12 days to complete a job. How long will 8 men take at the same... (answered by mananth)
It takes 4 men 14 days to do a certain job. How long should it take 7 men working at the... (answered by Maths68)
It takes 4 men 14 days to do a certain job. How long should it take 7 men working at the... (answered by josgarithmetic,rothauserc)
If m men do a job in 10 days, how long will it take 10 men to complete this task,... (answered by josgarithmetic)
15 men complete a job in 10 days, 8 men finish same job ? how many... (answered by josgarithmetic)
If 10 men working 8 hours a day take 15 days to complete a job.How long will it take 20... (answered by lwsshak3)