Question 89769: A&B working together can finish painting the house in six days. A, working alone, can finish it in five days less than B. How long will it take each of them to finish the work alone?
Answer by ankor@dixie-net.com(22740) (Show Source): You can put this solution on YOUR website!
A&B working together can finish painting the house in six days. A, working alone, can finish it in five days less than B. How long will it take each of them to finish the work alone?
:
Let x = A's time alone
then
(x+5) = B's time alone
:
Let the completed job = 1
:
+ = 1
:
multiply x(x+5) to get rid of the denominators
6(x+5) + 6x = x(x+5)
:
6x + 30 + 6x = x^2 + 5x
:
12x + 30 = x^2 + 5x
:
A quadratic equation:
x^2 + 5x - 12x - 30 = 0
:
x^2 - 7x - 30 = 0
:
(x - 10)(x + 3) = 0
:
x = 10 days, A alone (only solution that makes sense)
:
B = (x+5) = 15 days alone
:
:
Check our solutions:
+ =
+ = 1
RELATED QUESTIONS
A and B can finish the job in 6 days. A can work 5 days less than B. Find the number of (answered by ankor@dixie-net.com)
A can finish the work in 6 days less than the time taken by B to finish the work.If both... (answered by ankor@dixie-net.com)
1) Glenn can paint a house in 9 hours while Stewart can paint the same house in 16... (answered by Edwin McCravy)
It takes worker A six days longer as it takes worker B to finish a certain job. Working... (answered by greenestamps,ikleyn)
A and B can do a piece of work in 6 days, B and C can do it in 10 days and C and A can do (answered by richwmiller)
A and B can do a piece of work in 6 days, B and C can do it in 10 days and C and A do it... (answered by josgarithmetic)
A and B together can finish a piece of work in 12 days. it A alone can finish the same... (answered by ankor@dixie-net.com)
When workers A and B work together, they can finish the flooring of a house in 6... (answered by josgarithmetic,stanbon)
A and B working together can finish the job in 10 days. if A works 4 days and B works 3... (answered by josgarithmetic,ikleyn)