SOLUTION: Four A/C mechanics finish a job in 300 hrs. How much time will six A/C mechanics take to do the same job.

Algebra.Com
Question 895791: Four A/C mechanics finish a job in 300 hrs.
How much time will six A/C mechanics take to do the same job.

Answer by richwmiller(17219)   (Show Source): You can put this solution on YOUR website!
4*300=1200 mechanic hours needed for the job
1200/6=200 hours for 6 mechanics to do the same job


RELATED QUESTIONS

A can do a certain job in 4 hrs, B in 6 hrs, C in 8 hrs. How long will it take to do the... (answered by ptaylor)
A can do a certain job in 4 hrs, B can do the job in 6 hrs, and C can do the job in 8... (answered by josgarithmetic)
Thomas did a job in 4hrs and mary does the same job in six hrs how many hrs will it take... (answered by richwmiller)
A,B,and C can finish a job in six days. If B and C work together, the job will take 9... (answered by ankor@dixie-net.com,josmiceli)
three machines A , B and C take 3 hours to do a job, when working together. Suppose A and (answered by ankor@dixie-net.com)
If 3 men can do a job in 1 hour. How much time will it take 12 men to do the same... (answered by josgarithmetic)
"Three printing presses can finish a certain job in 90 minutes . How many minutes will it (answered by fractalier)
x does a job in 6 days. Y does the same job in 3 days. If they do the job together, how... (answered by checkley77,caet)
Gian and Arwin can finish a project in 4 2/3 hours. Gian can do it alone in half as much... (answered by ptaylor)