Question 895790: 25 workers can complete a work in 30 hours find the no. of hours required to complete same work by 10 workers
Answer by richwmiller(17219)   (Show Source): You can put this solution on YOUR website!
I wrote your question in English. you copied and pasted it wrong.
25*30=750 man hours
750/10=75 hours for 10 workers

RELATED QUESTIONS

15 workers can build a wall in 48 hours . how many workers will be required to do the... (answered by ankor@dixie-net.com)
30 workers complete a work in 15 days and 36 workers to complete same work in how many... (answered by chibisan)
16 workers can complete a piece of work in 30 days.After working for 10 days, 4 more... (answered by richwmiller,ikleyn)
If a crew of 4 workers complete the job in 10 hours, how long will it take 5 workers to... (answered by addingup)
If totally 25 workers working for 7 hours a day completing a particular piece of work in... (answered by ankor@dixie-net.com)
Three workers can complete a job in 3 hours, 5 hours, and 6 hours, respectively. How... (answered by Earlsdon)
Three workers can complete a job in 3 hours, 6 hours, and 8 hours respectively. How long... (answered by TimothyLamb,ewatrrr)
If 9 workers complete the work in 10 days how many workers will complete the same work in (answered by josgarithmetic,josmiceli)
In doing a project, a group of workers can complete the work in a certain number of days. (answered by scott8148)