Question 895471: A car park was built by 3men in 12 days how long will it take 1 man if he works at the same rate?
Answer by JulietG(1812) (Show Source): You can put this solution on YOUR website!
3 men * 12 days = 36 days' worth of work
Assuming the men work at the same rate, it will take that one poor guy 36 days to complete the car park.
RELATED QUESTIONS
If a wall was built by 4 men and 2 women in 5 days
how many days it will take to built... (answered by bucky,Theo)
8 men can dig a garden in 20 days. After working for 5days, 3men left. How long will it... (answered by josmiceli)
a man works for 6 days and is paid $153.How much would he paid for working 12 days at... (answered by Cromlix)
It takes nine days for 8 worker to pave a stretch of road. If each worker works at the... (answered by Mathtut)
of 5x workers can build a car in 4y days how many days will it take 2z work at the same... (answered by josgarithmetic)
If 6 men can dig a hole in 10 days how many days will it take 12 men to dig the same hole (answered by ikleyn)
Joe and Al work together for 4 hours to fix a car. If joe works alone, he can fix the car (answered by ikleyn)
One man can dig a canal in 60 days. How many days will 5 men take if they work at the... (answered by stanbon)
If 10 men can do lawn in 4 days how long will it take 8 men at the same rate
(answered by ikleyn)