Question 892082: A can do a piece of work in 16 days. After working on it for 4 days B joins who can complete work in 32 days. if A earns 1200 how much does B earn ?
Answer by josgarithmetic(39623) (Show Source): You can put this solution on YOUR website!
No clue how pay rate is related between A and B or to the work. Maybe just assumption of equal pay per time.
Are they paid at the same hourly rate?
WORK RATES:
A,
B,
A&B,
They complete 1 job in a combination of persons and days.
A for 4 days and then A&B for 32 days.
RT=J, for rate, time, job.
Solve this equation for x. The time for B to do the 1 job alone would be x days.
When you know x, you can find the work rate for B and the work rate of A and B combined.
THE ACTUAL QUESTION ASKED:
Your question was about pay rate and how much money B received. If both A and B get the same
daily rate of pay, then The pay rate for either of them is doller per day, based on the time and moneys
that A worked and received.
ANSWER:_____B worked for 32 days (while working together with A). B would earn
Apparently, solving for the time for B to do 1 job alone is not needed for finding how much he earns
in his 32 days of work.
RELATED QUESTIONS
1.'A' works twice as fast as 'B'. If both of them together take 6 days to complete the... (answered by josmiceli,vvnrichards)
A can do a work in 12 days ;B in 6 days and C in 3 days.A and B start working together... (answered by Edwin McCravy)
A and B together can do a piece of work in 12 days, which B and C together can do in 16... (answered by KMST)
16 workers can complete a piece of work in 30 days.After working for 10 days, 4 more... (answered by richwmiller,ikleyn)
Theresa can do a piece of work in 15 days. After she has worked 3 days, Rowena joins her... (answered by VFBundy,greenestamps,josgarithmetic)
Alan can do a piece of work in 15 days; Bill can do it in 20 days. If Alan works alone on (answered by josmiceli)
Ashraf and Bahar together can do a piece of work in 12 days, which Bahar and Charles... (answered by lwsshak3)
Eric and Nathan together can do a piece of work in 3 days. If it takes Eric working alone (answered by josgarithmetic)
A can do a piece of work in 16 days and B can do it in 20 days. These worked together for (answered by robertb)