SOLUTION: if one person can complete a task in 2h and another person can complete the same task in 3h, will it take more or less than 2h to complete the task when both people are working?

Algebra.Com
Question 890685: if one person can complete a task in 2h and another person can complete the same task in 3h, will it take more or less than 2h to complete the task when both people are working?
Found 2 solutions by richwmiller, lwsshak3:
Answer by richwmiller(17219)   (Show Source): You can put this solution on YOUR website!
it will be a little less than 2 hours.
1/2+1/3=1/x
3/6+2/6=1/x
5/6=1/x
6/5=x
1.2= x


Answer by lwsshak3(11628)   (Show Source): You can put this solution on YOUR website!
if one person can complete a task in 2h and another person can complete the same task in 3h, will it take more or less than 2h to complete the task when both people are working?
***
sum of individual work rates=work rate working together
1/2+1/3=1/x
3/6++2/6=1/x
5/6=1/x
x=6/5
it will take less than 2h to complete the task when both people are working

RELATED QUESTIONS

One person can complete a task in 3 minutes. A second person can complete the same task... (answered by ankor@dixie-net.com)
one person can complete a task 8 hours sooner than another person. working together both (answered by josmiceli)
It takes person A 4 hours less than person B to complete a certain task. Working... (answered by josmiceli)
It takes a more experienced person 1 hour less to complete a task than it does a less... (answered by ptaylor)
How long will it take workers to complete a task, given that workers can complete the... (answered by JulietG)
Working together, two people can complete a task in 9 hours. Working alone, one person... (answered by solver91311)
Machine X can complete a task in five minutes. Machine X and Machine Y, working togather... (answered by ewatrrr,richwmiller)
Working together, two people can complete a task in 10 hours. Working alone, one person... (answered by scott8148)
Ho long will it take 6 workers to complete a task, give that 7 workers can complete the... (answered by solver91311,Edwin McCravy,stanbon)