Question 888402: If m men do a job in 10 days, how long will it take 10 men to complete this task, assuming that they work at the same rate?
a)10/m
b)100/m days
c)100m days
d)m/100 days
e)m days

Answer by josgarithmetic(39617)   (Show Source): You can put this solution on YOUR website!
m men needing 10 days to do 1 job means our focus can be on doing 1 job.

Let r = rate of work for 1 man.

, and now t is time in days. We want to solve for t.



RELATED QUESTIONS

10 men can complete a job in 14 days. How long will it take 4 men to finish the same job... (answered by josgarithmetic)
10 men can complete a job in 14 days.how long will it take 4 men to finish same job if... (answered by josmiceli,josgarithmetic)
If it take four men a day's work to complete a specific task, how long will it take... (answered by richwmiller,ewatrrr)
If 6 men and 5 women complete a task in 6 days while the same task complete by 3 men and... (answered by richwmiller)
If 20 men can complete a piece of job in 8days, how long will it take 10 men to finish... (answered by Theo)
It takes 5 men to paint 2 identical houses in 3 days. Assuming that all men work at the... (answered by stanbon)
If 10 men can do lawn in 4 days how long will it take 8 men at the same rate (answered by ikleyn)
It takes 4 men 6 hours to repair a road. How long will it take 7 men to do the job if... (answered by lenny460)
Suppose that m people can do a task in d days. Assuming that they all work at the same... (answered by mananth)