SOLUTION: One factory takes four days to produce an airplane, another takes five, and a third takes seven days. How long does it take the three factories combined to produce eighty-three

Algebra.Com
Question 886219: One factory takes four days to produce an airplane, another takes five, and a
third takes seven days. How long does it take the three factories combined to
produce eighty-three airplanes?

Found 3 solutions by stanbon, Tanzina ahamed, MathTherapy:
Answer by stanbon(75887)   (Show Source): You can put this solution on YOUR website!
One factory takes four days to produce an airplane, another takes five, and a
third takes seven days. How long does it take the three factories combined to
produce eighty-three airplanes?
Let "x" be the number of days.
Rate for each factory::
1/4 plane per day
1/5 plane per day
1/3 plane per day
---------------------
Equation:
(1/4)x + (1/5)x + (1/3)x = 83
Multiply thru by 60 to get:
15x + 12x + 20x = 83*60
47x = 83*60
x = 105.96 days
Cheers,
Stan H.

Answer by Tanzina ahamed(5)   (Show Source): You can put this solution on YOUR website!
The above ans of Stan H is wrong.
Let x be the number of days.
Rate for each factory
1/4 plane per day
1/5 plane per day
1/7 plane per day
Therefore,
(1/4)x+(1/5)x+(1/7)x=83
multiply by 140 to get
35x+28x+20x=83*140
=>63x=11620
=>x=184.444 days

Answer by MathTherapy(10556)   (Show Source): You can put this solution on YOUR website!

One factory takes four days to produce an airplane, another takes five, and a
third takes seven days. How long does it take the three factories combined to
produce eighty-three airplanes?

Time to make 83 planes: days
You can do the check!!
If you need a complete and detailed solution, let me know!!
Send comments, “thank-yous,” and inquiries to “D” at MathMadEzy@aol.com.
Further help is available, online or in-person, for a fee, obviously.
For FREE info and answers to questions about the ASVAB exam, the NYS 3 – 8 city/state wide exams,GENERAL
MATH and HOMEWORK QUESTIONS, or MATH QUESTIONS related to the Regents Integrated Algebra,
Regents Geometry, Regents Algebra 2/Trigonometry, SHSAT, COOP/HSPT/TACHS, PSAT, SAT, ACT, SSAT/ISEE,
GRE, CLEP, and the TASC/GED, you can visit: http://asvabstudyzone.freeforums.net/.
RELATED QUESTIONS

It takes five men one hundred and twenty days to bild a shed, how many days does t take... (answered by Alan3354)
A day laborer takes three more days to paint a house than an apprentice painter. A master (answered by ptaylor)
It takes 3 painters 10 days to paint a house. How long does it take five painters to do... (answered by Edwin McCravy)
It takes Tom 2 days to paint a house and it takes Leah 4 days and it takes Lisa 6 days.... (answered by stanbon,jainenderkapoor)
If a man takes 7 days to dig his garden and the son takes 4 days. How long would it take... (answered by tommyt3rd)
It takes 5 men to build a shed in 120 days, how long does it take 3... (answered by Tatiana_Stebko)
If it takes workers A and B 2 days to complete a job. And it takes workers B and C 3 days (answered by ankor@dixie-net.com)
If it takes twelve men 8 days to dig a trench how many men does it take in 6... (answered by josgarithmetic)