SOLUTION: How many days will 1200 persons take to construct a bridge, if 450 persons can build the same in 45 days?

Algebra.Com
Question 886201: How many days will 1200 persons take to construct a bridge, if 450 persons can build the same in 45 days?
Answer by Edwin McCravy(20062)   (Show Source): You can put this solution on YOUR website!

Two ways to work it.

First way:

The LCM of 1200 persons and 450 persons is 3600 persons.

3600 persons is 3 times as many persons as 1200 persons and
3600 persons is 8 times as many persons as 450 persons.

Since 450 persons can build 1 bridge in 45 days, then 

3600 persons can build 8 bridges in 45 days.

So only 1200 persons will take 3 times as long or 135 days to build 8 bridges.

So to build only 1 bridge it will take 1200 persons only 1/8th as long,
and
1/8th of 135 days is 135/8 =  days.

------------------------------------------------------

Second way:

You can also use the worker-time-job formula, which is:



where

W1 = the number of workers in the first situation.
T1 = the number of time units (days in this case) in the first situation.
J1 = the number of jobs in the first situation.

W2 = the number of workers in the second situation.
T2 = the number of time units (days in this case) in the second situation.
J2 = the number of jobs in the second situation.

W1 = 1200             W2 = 450     
T1 =  ? (unknown)     T2 = 45
J1 =  1               J2 = 1









Reduce that fraction by dividing numerator and
denominator by 150



 days

Edwin



RELATED QUESTIONS

If 1200 persons can finish the construction of a building in 40 days, how many persons... (answered by richwmiller)
If one sack of rice can be consumed by 3 persons in 36 days, in how many days will 9... (answered by josgarithmetic)
of 5x workers can build a car in 4y days how many days will it take 2z work at the same... (answered by josgarithmetic)
15 persons can do the job in 6 days, how many extra persons are required if it would have (answered by nyc_function)
if 10 persos done a job in 18 days then 12 persons done the same job in how many... (answered by josgarithmetic)
4 men can build a shed in 12 days. How many men will it take to build the same shed in 3 (answered by josmiceli)
30 workers can construct a bridge in 84 days. After working for 36 days 10 left. How long (answered by richwmiller)
60 persons can complete a building in 250 days . after 200 days , work stopped for 10... (answered by ewatrrr)
if 20 men can build a wall in 5 days how many men will be required to build the same wall (answered by Theo)