SOLUTION: If a crew of 9 workers can paint a house in 14 days. How long will it take a crew of 5 to complete the same job? Given that the rate of work is the same per worker.

Algebra.Com
Question 885414: If a crew of 9 workers can paint a house in 14 days. How long will it take a crew of 5 to complete the same job? Given that the rate of work is the same per worker.
Answer by ankor@dixie-net.com(22740)   (Show Source): You can put this solution on YOUR website!
If a crew of 9 workers can paint a house in 14 days.
Find how many man-days required to paint the house
9 * 14 = 126 man-days to complete a house
:
How long will it take a crew of 5 to complete the same job? Given that the rate of work is the same per worker.
let d = no. of days required for 5 men to do the same job
5d = 126
d = 126/5
d = 25.2 days

RELATED QUESTIONS

If a crew of 4 workers complete the job in 10 hours, how long will it take 5 workers to... (answered by addingup)
All members of a crew work at the same pace. If only 4 of them are working, they complete (answered by josgarithmetic)
To complete a job a crew of 8 people needs 18 days. How long will the same job be... (answered by josgarithmetic)
SOPPOSE 4 PEOPLE CAN PAINT A HOUSE IF THEY WORKK 3 DAYS EACH. HOW LONG WOULD IT TAKE OF A (answered by josmiceli)
Suppose 4 people can paint a house if they work 3 days each. How long would it take a... (answered by stanbon)
One crew can detassel a field of corn in 6 days. Another crew can do the same job in 4... (answered by ankor@dixie-net.com)
All members of a crew work at the same pace. If only 4 members of the crew are working,... (answered by macston)
All members of a crew work at the same pace. If only 4 members of the crew are working,... (answered by josmiceli)
It took a crew of 16 workers 2.75 days to do 1/2 the job. Working at the same rate, how... (answered by josgarithmetic,josmiceli)