| 
 
 
 
Question 884284:  4 men and 10 women were put on a work. They completed 1/3 of the work in 
4 days. After this 2 men and 2 women were increased. They completed 2/9 
more of the work in 2 days. If the remaining work is to be completed in 3 
days, then how many more women must be increased ?
 
The answer is 8. I need the solution. 
 
Thank You. 
 Answer by josgarithmetic(39630)      (Show Source): 
You can  put this solution on YOUR website! RT=J Basic Equation, rate, time, job.
 
 
Let m = rate for 1 man 
Let w = rate for 1 woman
 
Each work session is build on a term RT but specifically these are in parts of 1/3, 2/9, and the remaining part of the job to make one whole job.
 
 
  
- 
  
- 
How many more men, working 3 more day? 
Let q = the additional number of men 
  
- 
BE SURE YOU UNDERSTAND EACH OF THOSE THREE EQUATIONS BEFORE CONTINUING.  The first is accounting for the amount of work in the first four days; the second is accounting for the work in the next two day; the last is accounting for the last portion of the work using unknown q increased men in that last three days of work.  
 
 
Observe how those THREE equations use THREE unknown variables.  This appears to NOT be a linear system.  This should not be a major difficulty because the first two equations form a system of TWO equations in TWO unknowns, m and w, to be found first.
 
 
 
SIMPLIFY THE WHOLE SYSTEM: 
  
  
- 
  
  
  
- 
  
  
  
and because we really will later want to solve for q, 
  
  
  
The simplified equations are shown outlined in  .
 
 
SOLVE THE SYSTEM: 
First solve for m and w in the first two equations as a separate subsystem.  I suggest substitution method because the coefficients are not very convenient for using elimination method. 
USE the values for m and w found, and compute the value for q.
 
 
The rest of that "SOLVE THE SYSTEM" work is undone here but you should (need ) to do it.   
  | 
 
  
 
 |   
 
 |   
 |  |