SOLUTION: If 10 boys clear a plot of land for 60minutes, how many minutes would it take 15 boys to clear that same plot of land?
Algebra.Com
Question 881568: If 10 boys clear a plot of land for 60minutes, how many minutes would it take 15 boys to clear that same plot of land?
Answer by JulietG(1812) (Show Source): You can put this solution on YOUR website!
It takes 600 minutes' worth of work to clear that plot.
10 boys do it in 60 minutes (10*60=600)
If 15 boys are working, it will take 600 / 15, or 40 minutes to clear the same amount.
RELATED QUESTIONS
if a man clear a plot of land at 3 hours, another man clear a plot of land at 5 hours and (answered by TimothyLamb)
Two companies working together can clear a parcel of land in 15 hours. Working alone, it (answered by ikleyn,Alan3354)
If five people clear a portion of grass on a land for twelve hours,how many hours would... (answered by josmiceli)
Two companies working together can clear a parcel of land in 13 hours. Working alone, it (answered by VFBundy,MathTherapy)
Two companies working together can clear a parcel of land in 18 hours. Working alone, it (answered by greenestamps)
Two companies working together can clear a parcel of land in 13 hours. Working alone, it... (answered by josmiceli)
Two companies working together can clear a parcel of land in 27 hours . Working alone it... (answered by greenestamps,richwmiller)
A triangular plot of land is drawn below. How much would it cost to put a fence around... (answered by oberobic)
If 3 men can clear land of200m in 15days, how long will 5men take to clear the same... (answered by ikleyn)