SOLUTION: if 6 men work 6 hours per day, they can finished a job in 6 days. how many days are needed to finish the same job if only 3 men work 2 hours per day
Algebra.Com
Question 881036: if 6 men work 6 hours per day, they can finished a job in 6 days. how many days are needed to finish the same job if only 3 men work 2 hours per day
Found 2 solutions by lwsshak3, josgarithmetic:
Answer by lwsshak3(11628) (Show Source): You can put this solution on YOUR website!
if 6 men work 6 hours per day, they can finished a job in 6 days. how many days are needed to finish the same job if only 3 men work 2 hours per day
***
Answer by josgarithmetic(39617) (Show Source): You can put this solution on YOUR website!
The one job using 6 men is done in hours. One man would do this job in jobs per hour rate. This one-man rate is jobs per hour.
Three Men group:
How many hours?
, t is time in hours.
hours.
How many days, if 1 day = 2 hours?
DAYS
RELATED QUESTIONS
If 54 men working 10 hours a day can finish a work job in 15 days, how many men are... (answered by Alan3354)
12 men working 7 hours a day can finish a job in 6 days. How many more hours a day must 8 (answered by ankor@dixie-net.com)
1.'A' works twice as fast as 'B'. If both of them together take 6 days to complete the... (answered by josmiceli,vvnrichards)
10 men can complete a job in 14 days. How long will it take 4 men to finish the same job... (answered by josgarithmetic)
A block industry estimates that 10 men must work for 8 hours each day to complete a job... (answered by ankor@dixie-net.com)
A cement factory estimates that 10 men must work for 8 hours each day to complete a job... (answered by josgarithmetic)
If a certain job can be finished by 18 workers in 26 days. How many workers are needed to (answered by robertb)
It takes Victor 6 days more to paint a house than Roger. If they work together, they can... (answered by rothauserc,ikleyn)
If 3 workers take 8 days to complete a job how many workers would be needed to finish the (answered by ewatrrr)