SOLUTION: 60 persons can complete a building in 250 days . after 200 days , work stopped for 10 days . how many additional men required to finish it on same time

Algebra.Com
Question 879395: 60 persons can complete a building in 250 days . after 200 days , work stopped for 10 days . how many additional men required to finish it on same time

Answer by ewatrrr(24785)   (Show Source): You can put this solution on YOUR website!


, 15 additional men needed

RELATED QUESTIONS

a contractor contract to build a house in 30 days after 20 days 10 men complete 1/3 work... (answered by josgarithmetic)
1.'A' works twice as fast as 'B'. If both of them together take 6 days to complete the... (answered by josmiceli,vvnrichards)
20 men can finish a work in 30 days. On completion of 10 days, 10 men leave work.... (answered by richwmiller)
15 men can do a work in 210 days.if 15 additional men engaged every after 10 days, in how (answered by ikleyn)
15 men can do a work in 210 days.if 15 additional men engaged every after 10 days, in how (answered by ankor@dixie-net.com)
10 men working 5 hrs per day can complete a pice of work in 12 days. How many men will be (answered by ankor@dixie-net.com)
A contractor engaged 30 persons to construct the road in 30 days but only one fourth of... (answered by jorel555)
18 men can dig a ditch in 10 days. After they have worked for 4 days how many more men... (answered by ankor@dixie-net.com)
if 15 men can do a work in 210 days . they started working but at the end 10 days 15... (answered by josgarithmetic)