SOLUTION: A can do a work in 12 days and B in 18 days. A started the work and B joined him later. Find when did B join A, if the entire work is completed in 8 days?

Algebra.Com
Question 876671: A can do a work in 12 days and B in 18 days. A started the work and B joined him later. Find when did B join A, if the entire work is completed in 8 days?
Found 2 solutions by ankor@dixie-net.com, LinnW:
Answer by ankor@dixie-net.com(22740)   (Show Source): You can put this solution on YOUR website!
A can do a work in 12 days and B in 18 days.
A started the work and B joined him later.
Find when did B join A, if the entire work is completed in 8 days?
:
let t = time worked before B joined A to finish the job
let the completed job = 1
:
+ = 1
multiply by 36 to clear the denominators
3(8) + 2(8-t) = 36
24 + 16 - 2t = 36
40 - 2t = 36
-2t = 36-40
-2t = -4
t = +2 days when B joined A to finish the job

Answer by LinnW(1048)   (Show Source): You can put this solution on YOUR website!

A has a rate of 1/12 work per day
B has a rate of 1/18 work per day
(1/12)(time) + (1/18)(time - B's delay) = 1 task
The time is 8 days
set x = B's delay
(1/12)(8) + (1/18)(8 - x) = 1
8/12 + 8/18 - (1/18)x = 1
2/3 + 4/9 - (1/18)x = 1
multiply each side by 18
18(2/3 + 4/9 - (1/18)x ) = 1* 18
36/3 + 72/9 - x = 18
12 + 8 - x = 18
20 - x = 18
add -20 to each side
-x = -2
x = 2
So B joins A 2 days after the start
Checking,
(1/12)(8 days) + (1/18)(6 days) ?= 1
8/12 + 6/18 ?= 1
2/3 + 1/3 = 1
So our answer is correct

RELATED QUESTIONS

A can do a piece of work in 4 1/2 days. After he has worked three days, B joined him and... (answered by richwmiller)
A can do a certain job in 40days which b alone can do it in 30 days .A started the work... (answered by flame8855)
A and B can do a work in 12 days,B and C in 16 days. A started work and afte 7 days he... (answered by josgarithmetic)
'A' and 'B' together can complete a work in 3 days. They started together. But after 2... (answered by josgarithmetic)
Raja can do a piece of work in 20 days , while Ramesh can finish it in 25 days. ramesh... (answered by josgarithmetic,stanbon)
A and B can do a job in 12 days and B and C can do it in 16 days. A and B started... (answered by josgarithmetic)
A,B and C can finish a job in 6 days. If B and C work together, the job will take 9 days; (answered by stanbon,harshachittar)
if A , B , and C can work in 10 days A and C can work in 12 days A and B can work in... (answered by Edwin McCravy)
A can do a piece of work in 12 days and B can do a piece of work in 18 days. They started (answered by dkppathak)