Question 875164: A does 80% of a work in 20 days. He then calls in B and together they finish the remaining work in 3 days. How long B alone would take to do the whole work.
Answer by dkppathak(439) (Show Source): You can put this solution on YOUR website!
A does 80% of a work in 20 days. He then calls in B and together they finish the remaining work in 3 days. How long B alone would take to do the whole work.
A completed 80% work in 20 days
A can complete the full work in 25 days
A 1 day work will be =1/25 parts
task complete by A in 20 days =80/100 =4/5
remaining work =1-4/5 =1/5 (1)
let b can complete full work in X days
B 1 day work will be =1/X part
A and B 1 day work together will be = 1/25+1/x
= X+25/25X
A and B 3 days work will be = 3(x+25)/25x (2)
by given conditions equation 1 and 2 will be equal
1/5=3x +75/25x
25X = 5(3X +75)
25x= 15X + 375
25x-15x =375
10 X=375
X=37.5 days
B alone can complete whole work in 37.5 days OR 75/2 days Answer
RELATED QUESTIONS
A does 3/10 of a work in 6 days .He then calls in B and they finish the work in 7 days... (answered by ankor@dixie-net.com)
A does 4/5 of a work in 20 days.He then calls in B and together finish the remaining work (answered by ewatrrr)
A does 7/10 of a piece of work in 14 days. He then calls B, and they finish the work in 2 (answered by fractalier)
Bigyan can do of a work in 9 days. He calls Amar to finish the remaining work. They work (answered by Collinwilfixyouuprealnice)
A,B,C can finish a piece of work in 60 days. They work together for 10 days after which A (answered by htmentor)
Worker A can do a piece of work in 20 days. Workers A and B in 15 days.
They work... (answered by richwmiller)
A can do a work in 32 days and B in 40 days. they work together for 10 days and then B... (answered by mananth)
A & B together can paint a room in 18 days . they work together for 8 days and then b... (answered by richwmiller,josmiceli)
A can do a piece of work in 25 days and B can do a work in 20 days.both work together... (answered by ptaylor)