Answer by jim_thompson5910(35256)   (Show Source): You can put this solution on YOUR website!
x = time it takes for A to do the job alone
y = time it takes for B to do the job alone
z = time it takes for them to get the job done when they work together. This is assuming that one person doesn't slow the other down and they work in the most efficient way as a team.


When we make those definitions above, it turns out that we can tie x,y,z together with this equation




In this case,


x = 10
y = unknown (leave it as y for now)
z = 6


Plug those into the equation and solve for y























So it will take 15 days for B to do the job alone.

RELATED QUESTIONS

A and B can do a job in 6 days.If A do the job alone he takes 10 days.What will be the... (answered by harpazo)
A and B can do work in 6 days. if A works alone he takes 10 days. what will be the time... (answered by josmiceli)
A and B can do work in 6 days. if A works alone he takes 10 days. wahat will be the time... (answered by robertb)
1.'A' works twice as fast as 'B'. If both of them together take 6 days to complete the... (answered by josmiceli,vvnrichards)
A takes 10 more days to do a job than B they both do a job in 12 days. in how many days B (answered by ikleyn,Theo)
A can complete a job in 9 days, B can do the same job in 10 days and C can do it in 15... (answered by richwmiller)
If it takes workers A and B 2 days to complete a job. And it takes workers B and C 3 days (answered by ankor@dixie-net.com)
Workers A and B can complete a particular job if they work together for 12 days. If A... (answered by richwmiller)
a and b can each do a piece of work in 15 days and 18 days. if a works for 10 days, how... (answered by stanbon)