Question 864543: If it take four men a day's work to complete a specific task, how long will it take sixteen men to complete double the task assuming they work at the same rate
Found 2 solutions by richwmiller, ewatrrr:
Answer by richwmiller(17219)   (Show Source): You can put this solution on YOUR website!
4 men one day to finish a task
4 men two days for double the task
or
8 men for double the task in one day
16 men to finish double the task in 1/2 day.




Answer by ewatrrr(24785)   (Show Source): You can put this solution on YOUR website!

.5 days

RELATED QUESTIONS

If it takes 10 men 4 hours to repair a barn, how long will it take 8 men to complete the... (answered by solver91311)
If 4 men clean a house in 150 minutes, how long will it take 5 men to complete the same... (answered by stanbon)
If 6 men and 5 women complete a task in 6 days while the same task complete by 3 men and... (answered by richwmiller)
If 10 men working 8 hours a day take 15 days to complete a job.How long will it take 20... (answered by lwsshak3)
if it takes 4 men 6 hours to landscape a recreation area, how many hours will it take 3... (answered by harpazo)
10 men can complete a job in 14 days. How long will it take 4 men to finish the same job... (answered by josgarithmetic)
if 8 men can do a job in 12 days how long will 24 men take to complete it (answered by amarjeeth123)
10 men can complete a job in 14 days.how long will it take 4 men to finish same job if... (answered by josmiceli,josgarithmetic)
It takes 10 days for 4 men working 6 hours a day to complete some work. How many days... (answered by josgarithmetic)