Question 851988: if a man can dig a pit in 10 days while onother man can do it in 20 days.how long will they take to do the work if they do it together?
Answer by josh_jordan(263)   (Show Source): You can put this solution on YOUR website!
To solve, we need to set this word problem as an equation.

1. If one man can dig a pit in 10 days, he can dig 1/10 of the pit per day.

2. If another man can dig a pit in 20 days, he can dig 1/20 of the pit per day.

So, we can set up the equation as follows:



Now, we can solve for x, which will tell us how long it would take if the two men worked together. To do this, first multiply each fraction by the LCD of all of the fractions, which is 20x. This will give us:

2x + x = 20 ----->

3x = 20 ----->

x = 20/3 ----->

x ≈ 6.67 days

RELATED QUESTIONS

One man can dig a canal in 60 days. How many days will 5 men take if they work at the... (answered by stanbon)
Two digging crews are competing for a job the first team shows they can dig a foundation... (answered by josgarithmetic)
Four men working together can dig a ditch in 42 days. They begin, but one man works only... (answered by ankor@dixie-net.com)
if 12men can dig a pit in 5days. how many more men do you require to do the same work in... (answered by solver91311)
alma can do a job in 6 days. rachel can do job in 12 days. how long it will take if they... (answered by nihar*2013)
If 2 men take 8 days to mow a field and the faster man can do it alone in 12 days how... (answered by ankor@dixie-net.com)
If a man takes 7 days to dig his garden and the son takes 4 days. How long would it take... (answered by tommyt3rd)
Ramesh , Suresh and Harish can do a piece of work in 15 days, 10 days and 6 days... (answered by mananth)
Alma can do the job in 6 days while Rachel can do the same. In 12 days. How long will it... (answered by Cromlix)