Question 850992: A is thrice as good as workman as B and therefore is able to finish a job in 60 days less than B. Working together, they can do it in:
Answer by richwmiller(17219)   (Show Source): You can put this solution on YOUR website!
a=b-60,
a=b/3
b-60=b/3
3b-180=b
2b=180
b=90
a=30
1/30+1/90=1/x
3/90+1/90=1/x
4/90=1/x
1/15=1/x
x=15 days together






RELATED QUESTIONS

a b and c working together complete a job in 18 days. A and B together work twice as much (answered by richwmiller)
A computer encoder A can finish a job in as many days as encoder B. Encoder C can finish... (answered by richwmiller)
Computer encoder A can finish a job in as many days as encoder B. Encoder C can finish... (answered by Theo)
It takes worker A six days longer as it takes worker B to finish a certain job. Working... (answered by greenestamps,ikleyn)
Dear... A finishes a paint job in two hours less than B. C paints as quickly as A and B (answered by josgarithmetic)
The workman A finishes the job 2 hours faster than the workman C, and 1 hour slower than... (answered by josgarithmetic,josmiceli)
1.) Roland takes twice as much time as Michael and thrice as much time as Eze to complete (answered by Fombitz)
Two workmen have to finish a job. If they work together the job will be done in 12 days.... (answered by josgarithmetic)
If Team A and Team B work together, they can finish a project in 6 days. Team A is twice... (answered by ikleyn)