SOLUTION: If a worker can wash all the glass windows of a building in 9 days, what part of the job can said worker finish in 6 days?

Algebra.Com
Question 848718: If a worker can wash all the glass windows of a building in 9 days, what part of the job can said worker finish in 6 days?
Answer by richwmiller(17219)   (Show Source): You can put this solution on YOUR website!
He does 1/9 each day so in 6 days he does 6/9=2/3
RELATED QUESTIONS

If a worker can wash all the glass windows of a building in 9 days, what part of the job... (answered by jim_thompson5910)
A worker can finish a job in 18 days.An other worker can do the same work but in 24 days... (answered by ptaylor)
Worker A and worker B, working together, can finish a job in 12 days. After 8 days worker (answered by josmiceli)
A painter can paint a building in 15 days and a co-worker can do the same job in 10 days. (answered by ikleyn)
When workers A and B work together, they can finish the flooring of a house in 6... (answered by josgarithmetic,stanbon)
A painter can paint a building in 15 days and a co worker can do the same job in 10 days. (answered by josgarithmetic,ikleyn)
Two workers finished a job in 7.5 days. How long would it take each worker to do the job... (answered by ankor@dixie-net.com)
A worker can do a work in 18 days . An oher worker can do the same work but in 24 days... (answered by oscargut)
i have solved that if Worker A finishes a job in 8 days and worker B finishes it in 12... (answered by josmiceli)