Answer by richwmiller(17219)   (Show Source): You can put this solution on YOUR website!
15*6=90 worker hours
15 hours for 6 workers

RELATED QUESTIONS

If 8 assemblers can complete a certain job in 9 ​hours, how long will the same job... (answered by Fombitz)
if 24 assemblers can complete a certain job in 6 hours, how long will it take if the... (answered by ewatrrr)
If 30 assemblers can complete a certain job in 4 ​hours, how long will the same job (answered by josgarithmetic)
melanie can do a job in 4 hours. kim can do the same job in 6 hours. if they work... (answered by mananth)
Suppose an average professor can do a certain job in nine hours and an average student... (answered by ikleyn)
If a crew of 4 workers complete the job in 10 hours, how long will it take 5 workers to... (answered by addingup)
Jake can complete a job in 5 hours while Jerry can complete the same job in 3 hours. How... (answered by deepikabansal)
jake can complete a job in 5 hours while jerry can complete the same job in 3 hours. how... (answered by stanbon)
Jake can complete a job in 5 hours while Jerry can complete the same job in 3 hours... (answered by richwmiller)