Question 842705: how long will it take 8 workers to complete a job that took 5 workers to complete in 10 days
Answer by richwmiller(17219) (Show Source): You can put this solution on YOUR website!
5 workers in 10 days is 5*10=50 worker days
50/8=6.25 days to complete the job.
RELATED QUESTIONS
If it can take 10 days for 5 workers to complete a job, how long will it take 8 workers... (answered by ewatrrr)
How long will it take workers to complete a task, given that workers can complete the... (answered by JulietG)
If a crew of 4 workers complete the job in 10 hours, how long will it take 5 workers to... (answered by addingup)
how long will it take 18 workers to complete a task, given that it take 9 days for 8... (answered by boilpoil)
If it takes 3 workers 15 days to complete a job, how long would it
take 5 workers to... (answered by AnlytcPhil)
If 15 workers can complete a job in 20 days, how long should it take 25 workers to... (answered by ankor@dixie-net.com)
it takes 12 workers 10 days to complete a piece of roadway how long will it take 5... (answered by richwmiller)
On an assembly line, five workers take six hours to complete a job. How long will it take (answered by josmiceli)
If 6 workers can complete 9 identical jobs in 3 days, how long will it take 4 workers to... (answered by solver91311)