SOLUTION: A can do a piece of work in 10 days. If A and B work together they can finish it in 6 days. find the work left in B alone will finish the work
Algebra.Com
Question 841522: A can do a piece of work in 10 days. If A and B work together they can finish it in 6 days. find the work left in B alone will finish the work
Answer by Narsinghchauhan8960103366(17) (Show Source): You can put this solution on YOUR website!
1 day work of A = 1/10
1 day work of A and B =1/6
1 day work of B = 1/6 - 1/10 = 1/15
So B can finish the work in 15 days.
RELATED QUESTIONS
A does 3/10 of a work in 6 days .He then calls in B and they finish the work in 7 days... (answered by ankor@dixie-net.com)
Please solve this question : two persons A and B together can do work in 10 days. the... (answered by richwmiller)
A can do a piece of work in 2 days as B can do in 3 days. B can do as much work in 4 days (answered by ankor@dixie-net.com)
A and B together can finish a piece of work in 12 days. it A alone can finish the same... (answered by ankor@dixie-net.com)
A and B can do a piece of work in 6 days, B and C can do it in 10 days and C and A can do (answered by richwmiller)
A,B and C can do a piece of work together in 15 days. B alone can do in 30 days and C... (answered by ankor@dixie-net.com)
A and B can do a piece of work in 6 days, B and C can do it in 10 days and C and A do it... (answered by josgarithmetic)
Worker A can do a piece of work in 20 days. Workers A and B in 15 days.
They work... (answered by richwmiller)
Joel can finish a work in 10 days, after he has worked for 2 days, Sam came to help him... (answered by richwmiller)