SOLUTION: 4 men or 6 boys can dig a well in 14 days . how long would 2 men and 4 boys take to dig the same well?

Algebra.Com
Question 838642: 4 men or 6 boys can dig a well in 14 days . how long would 2 men and 4 boys take to dig the same well?
Answer by ankor@dixie-net.com(22740)   (Show Source): You can put this solution on YOUR website!
4 men or 6 boys can dig a well in 14 days.
Find the number of man-days and boy-days required to complete the job
4 * 14 = 56 man-days
6 * 14 = 84 boy-days
:
Since they both worked 14 days to complete the job, we can say:
4m = 6b
2m = 3b
m = 1.5b
:
how long would 2 men and 4 boys take to dig the same well?
Use boy-days, replace men with 1.5
let d = no. of days required with this scenario
2(1.5)d + 4d = 84
3d + 4d = 84
7d = 84
d = 84/7
d = 12 days for 2 men and 4 boys to do the job

RELATED QUESTIONS

Four men can dig a 40 foot well in 4 days. How long would it take for 8 men to dig a 60... (answered by Alan3354,ankor@dixie-net.com)
7 men can dig a drain in 10 days. how many men would dig the same drain in 14 days (answered by josgarithmetic,ikleyn,greenestamps)
if 4 men work for 6 hours a day for 3 days to dig a hole. how long will it take 12 men to (answered by macston)
If 5 men dig a drain in 14 days, how long would 7 men take working at the same rate?... (answered by richwmiller)
6 men can dig a trench in 3 days. How many days will it take 9 men to dig the same trench (answered by Edwin McCravy)
If 6 men can dig a hole in 10 days how many days will it take 12 men to dig the same hole (answered by ikleyn)
If 3 men take 4 days to dig a drain how long would it take 2 men (answered by josgarithmetic)
if it takes 4 men 12 days to dig a hole, how long would it take 6... (answered by ptaylor)
20 men or 30 boys can do a certain job in 20 days. how long will it take 6 men and 15... (answered by ankor@dixie-net.com)