SOLUTION: Four men working together can dig a trench in 42 days. They begin the job, but one worker works only 1/2 days. How long will it take to complete the job?

Algebra.Com
Question 831014: Four men working together can dig a trench in 42 days. They begin the job, but one worker works only 1/2 days. How long will it take to complete the job?
Answer by josmiceli(19441)   (Show Source): You can put this solution on YOUR website!
The rate for 4 men is 1 trench in 42 days
Let = the fraction of a trench dug
by 4 men in 1/2 day



----------------
That means there is
of a trench left to dig after 1/2 day
----------------
3 men have to finish the job
If 4 men take 42 days to dig a trench,
1 man takes 4 times as long, or days
3 men take 1/3 of that time, or 56 days
Let = the number of days for 3
men to dig of the trench





It will take days
to finish the job
----------------------
Hope I got it

RELATED QUESTIONS

Four men working together can dig a ditch in 42 days. They begin, but one man works only... (answered by ankor@dixie-net.com)
Ten men can dig a trench in 4 days.How many men would dig the same trench in 2... (answered by Alan3354,ankor@dixie-net.com)
6 men can dig a trench in 3 days. How many days will it take 9 men to dig the same trench (answered by Edwin McCravy)
Tom, Dick, and Harry begin working together to dig a trench. Tom works twice as fast as... (answered by ankor@dixie-net.com)
Two men dig a trench 30 m long in 3 days. How long would it take 3 men to dig a trench 15 (answered by ikleyn)
If 12 men can dig a trench in 8 days how many men can dig it in 6... (answered by josgarithmetic,greenestamps)
It takes 4 men working full time 42 days to do a job. If 1 guy only works half the time,... (answered by josgarithmetic)
if 12 men can dig a trench in 8 days, how many men can dig it in 6 days at the same rate? (answered by josmiceli,ptaylor)
If 5 men dig a drain in 14 days, how long would 7 men take working at the same rate?... (answered by richwmiller)