Answer by richwmiller(17219)   (Show Source): You can put this solution on YOUR website!
12*20=240 man days
240/8=30 days for 8 men to complete the same job

RELATED QUESTIONS

If 15 men complete a work in 20 days;then 25 men will complete that work in how much... (answered by josgarithmetic)
If 15 men complete a work in 20 days then 25 men will complete that work in how much... (answered by FrankM,Edwin McCravy,AnlytcPhil)
if 5 men complete work in 100 days than how many men complete the same work in 20 days ? (answered by richwmiller)
a contractor took a work to complete in 17 days by 9 employee. in 8 days 2/5 work was... (answered by ankor@dixie-net.com)
If 15 men complete a work in 20 days, then how many men will be required to do the same... (answered by josgarithmetic)
12 women alone can complete a piece of work in 5 days, whereas 3 women and 9 children... (answered by knighty2002uk)
12 men can complete a work in ten days. 20 women can complete the same work in twelve... (answered by solver91311,josgarithmetic,MathTherapy)
In 5 days A can do as much work as B in 6 days. If they work together they can complete 1 (answered by richwmiller)
30 workers complete a work in 15 days and 36 workers to complete same work in how many... (answered by chibisan)