SOLUTION: If it takes 6 men 12 days to build a wall, how long will it take 12 men?

Algebra.Com
Question 824303: If it takes 6 men 12 days to build a wall, how long will it take 12 men?
Answer by fcabanski(1391)   (Show Source): You can put this solution on YOUR website!
The wall took a total of 6*12 = 72 man days to build.


1 (the job) = x * 72 where x is the rate each man works.


1/72 = x = the amount of the wall each man builds per day.


1/72 * 12 = 12/72 of the wall built (by 12 men) each day. We need a total of 72/72 (1) wall.


72/12 = 6 days for the 12 men to build the wall.


You can also look at it simple. 12 men complete the wall twice as fast as 6 men. They complete the job in half the time. So 12 men complete the wall in 12/2 = 6 days.

RELATED QUESTIONS

If it takes 3 men 4 days to build a wall how long will it take 2... (answered by stanbon)
It will take 12 men to build a wall in 30 days. How long should 8 men take to build a... (answered by Boreal)
If 3 men build a wall in 4 days how long will it take 5... (answered by josmiceli)
If it took 12 men 18 hours to build a wall , how long will it take 9 men to build it? (answered by Fombitz)
If it takes 10 men 12 hours to build a wall how long dose it take 8 men working at the... (answered by Theo)
if it takes 4 men 12 days to dig a hole, how long would it take 6... (answered by ptaylor)
It take 6 men 24 days to build a wall. How many days will it take 8 men to build the same (answered by malglu,jayesh.nandhu)
it takes 8 men to build a wall in 30 days. How long would it take 10 men to build the... (answered by JulietG)
If it takes 3 men 2 hours to build a wall, how long would it take 4 men? (answered by Cromlix)