SOLUTION: 12 men take 27 hours to paint a house. Given that all the men work at the same rate, find how long it will take 9 men to paint the same house. I would really appreciate your time a

Algebra.Com
Question 823903: 12 men take 27 hours to paint a house. Given that all the men work at the same rate, find how long it will take 9 men to paint the same house. I would really appreciate your time and effort if you could help me with this question. I really don't know a method to solve it. Thanks!
Found 2 solutions by josgarithmetic, richwmiller:
Answer by josgarithmetic(39617)   (Show Source): You can put this solution on YOUR website!
If only 1 of the men, then the work rate is of the group of 12 men. This means, 1 man goes at the rate of houses per hour. The question is about the rate for 9 men:

Knowing their rates are additive, houses per hour, which using the reciprocal, is 36 hours to paint one house.

Answer by richwmiller(17219)   (Show Source): You can put this solution on YOUR website!
find out the man hours needed to paint the house
12*27=324 man hours needed to paint the house
there are only 9 men available to do the 324 man hours
324/9=36 hours for 9 men

RELATED QUESTIONS

9 men took 20 hours to paint a house. If all the men work at the same rate, how many... (answered by Edwin McCravy)
It will take 24 men working 9 hours a day each to build a house in 45 days. Given that... (answered by lwsshak3)
It takes 5 men to paint 2 identical houses in 3 days. Assuming that all men work at the... (answered by stanbon)
if 5 men can build a house in 16 days how long will it take just 2 men to build the same... (answered by ankor@dixie-net.com)
If 8 men can chop 9 cords of wood in 6.5 hours, how long will it take 4 men to chop 3... (answered by ankor@dixie-net.com)
If 9 men take 15 days to tile the floors of a house, how long will it take five men... (answered by richwmiller)
three men paint a house in 5 days. How long will it take 2 men to paint the... (answered by ewatrrr)
three men paint a house in 5 days. how long will it take 2 men to paint the... (answered by Alan3354)
2 men take 16 hrs to paint a house. 4 women take 16 hrs. to paint a house. If a group (answered by josgarithmetic)