Question 815323: X can do 3/4 of a work in 12 days, he ca finish the 1/2 work in:..........................?
Answer by ewatrrr(24785)   (Show Source): You can put this solution on YOUR website!
 
Hi,
X can do 3/4 of a work in 12 days, he can finish the 1/2 work in "d" days.
|Cross Multiplying to solve

d = 8 days
RELATED QUESTIONS

If 4 men and 6 boys can finish a piece of work in 24 days, in what time will 8 men and 9... (answered by ankor@dixie-net.com)
A can do a piece of work in 2 days as B can do in 3 days. B can do as much work in 4 days (answered by ankor@dixie-net.com)
if a man can do a piece of work in 15 days what part of work does he finish in 1 day? in... (answered by josgarithmetic)
2 men and 5 boys together can a finish a piece of work in 4 days ,while 3 men and h boys... (answered by richwmiller)
Jack and Jill together can do a piece of work in 3 days. They can finish the work if... (answered by Edwin McCravy,ikleyn)
Bigyan can do  of a work in 9 days. He calls Amar to finish the remaining work. They work (answered by Collinwilfixyouuprealnice)
Theresa can do a piece of work in 15 days. After she has worked 3 days, Rowena joins her... (answered by VFBundy,greenestamps,josgarithmetic)
Amar can do a piece of work in 15 days. when he had worked for 3 days, sameer joined him... (answered by lwsshak3)
Pedro and Juan can do a piece of work in 3 and 3/7 days . If Pedro works in 3 days and... (answered by josgarithmetic)