SOLUTION: If 20 people did one work for 30 days to complete, then if the same work done by 25 people then how many days taken for that work?

Algebra.Com
Question 815306: If 20 people did one work for 30 days to complete, then if the same work done by 25 people then how many days taken for that work?
Answer by richwmiller(17219)   (Show Source): You can put this solution on YOUR website!
20*30=600 man days
600/25=24 days

RELATED QUESTIONS

1.'A' works twice as fast as 'B'. If both of them together take 6 days to complete the... (answered by josmiceli,vvnrichards)
If a work is done in 4 days by A and the same work is done in 12 days by B, then how many (answered by ewatrrr,richwmiller)
If 20 people complete the work in 30 days, then after how many days should 5 people go on (answered by richwmiller)
if a group of 15 person is required to work for 8 days to complete a project how many... (answered by josgarithmetic)
60 people can finish a work in 15 days. After doing 6 days of work, 12 people added to... (answered by ankor@dixie-net.com,richwmiller)
If 15 men complete a work in 20 days, then how many men will be required to do the same... (answered by josgarithmetic)
How to Solve? if 300 people eat an amount food for 90 days and after 20 days 50 people... (answered by richwmiller)
A can do a piece of work in 30 days,and B can do the same work in 40 days,if both do... (answered by richwmiller)
If 15 men complete a work in 20 days;then 25 men will complete that work in how much... (answered by josgarithmetic)