Question 811313: 5 men can complete a job in 4 days.In how many days can 10 men working at 1/4 of the previous rate complete the job.
Answer by josmiceli(19441) (Show Source): You can put this solution on YOUR website!
5 men can complete a job in 4 days
-------------
Twice as many men can do the same
job in half the time, so
-------------
10 men can do the job in 2 days
working at the same rate
-------------
Working at 1/4 of that rate, the
10 men take 4 times as long, so
-------------
10 men do the job in 8 days
RELATED QUESTIONS
5 men can complete a job in 4 days. How many days can 10 men working at 1/4 of the... (answered by josgarithmetic)
10 men can complete a job in 14 days. How long will it take 4 men to finish the same job... (answered by josgarithmetic)
1.'A' works twice as fast as 'B'. If both of them together take 6 days to complete the... (answered by josmiceli,vvnrichards)
eight men can complete a job in 25 days. how many men will be needed to complete the job... (answered by psbhowmick)
Hi
10 men and 20 women can do a job in 15 days. 15 men and 10 women can do the same job... (answered by VFBundy)
A job can be done by 15 men in 30 days. In how many days can 12 men complete the job,... (answered by Edwin McCravy)
If 54 men working 10 hours a day can finish a work job in 15 days, how many men are... (answered by Alan3354)
15 men complete a job in 10 days, 8 men finish same job ? how many... (answered by josgarithmetic)
If 20 men can complete a piece of job in 8days, how long will it take 10 men to finish... (answered by Theo)