Question 809501: A and B together can do a piece of work in 24/5 days B and C together can do it in 8 days and A B C together in 4 days , A and C together will finish in how many days ?
Answer by richwmiller(17219) (Show Source): You can put this solution on YOUR website!
24/5=4.8
4.8/a+4.8/b=1,
8/b+8/c=1,
4/a+4/b+4/c=1
a = 8, b = 12, c = 24
x/8+x/24=1
x=6
a and c together will finish the job in 6 days
RELATED QUESTIONS
A,B and C can do a piece of work together in 15 days. B alone can do in 30 days and C... (answered by ankor@dixie-net.com)
A and B together can do a piece of work in 12 days, which B and C together can do in 16... (answered by KMST)
A and B can do a piece of work in 42 days, B and C in 31 days and C and A in 20 days. In... (answered by Edwin McCravy,AnlytcPhil,Edwin Parker)
A and B can do a piece of work in 6 days,B and c together in 10 days,c and A together in... (answered by lwsshak3)
A,B and C can finish a job in 6 days. If B and C work together, the job will take 9 days; (answered by stanbon,harshachittar)
A and B can do a piece of work in 42 days, B and C in 31 days, and A and C in 20 days.... (answered by ptaylor,Edwin Parker)
A and B can do a piece of work in 6 days, B and C can do it in 10 days and C and A can do (answered by richwmiller)
a and b can do a piece of work in 18 days, b and c can do it in 24 days while c and a can (answered by richwmiller)
A and B can do a piece of work in 6 days, B and C can do it in 10 days and C and A do it... (answered by josgarithmetic)