SOLUTION: 10 men working 3 hrs a day can complete a wall in 8 days. How many men will be required to complete 3 wall of the same size in working 8 hrs a day?

Algebra.Com
Question 806193: 10 men working 3 hrs a day can complete a wall in 8 days. How many men will be required to complete 3 wall of the same size in working 8 hrs a day?
Found 2 solutions by josmiceli, richwmiller:
Answer by josmiceli(19441)   (Show Source): You can put this solution on YOUR website!
10 men do 1 wall in hrs
-------------
Note that hrs
------------------
1/5 as many men will take 5 times as long
to do 1 wall
------------------
So, 2 men do 1 wall in hrs
------------------
To do 3 walls in this time will take
3 times as many men, so
---------------------
6 men can complete 3 walls in 120 hrs,
or 15 days working 8 hrs a day

Answer by richwmiller(17219)   (Show Source): You can put this solution on YOUR website!
10*3*8=240 work hours to finish one wall
3 walls would be 720
15*8=120 per wall so we need 2 men per wall so we need 3*2= 6 men
also
720/120=6

RELATED QUESTIONS

10 men working 5 hrs per day can complete a pice of work in 12 days. How many men will be (answered by ankor@dixie-net.com)
If a group of 24 men working 8 hrs a day can complete building a wall in 12 days then in (answered by ankor@dixie-net.com,DEEPAK K)
1.'A' works twice as fast as 'B'. If both of them together take 6 days to complete the... (answered by josmiceli,vvnrichards)
if 20 men can build a wall in 5 days how many men will be required to build the same wall (answered by Theo)
if 20 men can build a wall in 5 days how many men will be required to build the same... (answered by greenestamps,ikleyn)
It takes 10 days for 4 men working 6 hours a day to complete some work. How many days... (answered by josgarithmetic)
12 men can build a wall in 4 days.how many days will 3 men take to build the same wall? (answered by josgarithmetic)
3 men and 7 women can complete a work in 10 days . But 4 men and 6 women need 8 days to... (answered by josmiceli)
Ten men working for 6 days of 10 hours each, finish 5/21 of a piece of work . How many... (answered by robertb,MathTherapy)