Answer by richwmiller(17219) (Show Source): You can put this solution on YOUR website!
20 people working 30 days are 600 man work days to finish the job.
If it were 5 days it would be
20*5=100 man work days.
15 people working for 30 more days
15 * 30=450 man work days
100+450=550
that only adds up to 550 man work days which isn't enough to finish the job.
The correct answer is
20x+15y=600,
x+y=35
x = 15, y = 20
5 people leave after 15 days
and 15 people finish the work in 20 more days
RELATED QUESTIONS
If 20 people did one work for 30 days to complete, then if the same work done by 25... (answered by richwmiller)
10 workers can do work in 20 days , when they start the work , after how many days... (answered by josgarithmetic,MathTherapy)
20 man can finish a work in 30 days.after how many days should 5 people goes the work... (answered by josgarithmetic)
1.'A' works twice as fast as 'B'. If both of them together take 6 days to complete the... (answered by josmiceli,vvnrichards)
60 people can finish a work in 15 days. After doing 6 days of work, 12 people added to... (answered by ankor@dixie-net.com,richwmiller)
if 5 men complete work in 100 days than how many men complete the same work in 20 days ?
(answered by richwmiller)
1. 20 men can do a piece of work in 30 days.After working for how many days should 5 men... (answered by josgarithmetic)
20 men can finish a work in 30 days. On completion of 10 days, 10 men leave work.... (answered by richwmiller)
Hi I really need help with these questions please. Could someone show their solution too... (answered by richwmiller)