Answer by solver91311(24713)   (Show Source): You can put this solution on YOUR website!
 
Three people can do 1/8th of the job in 1 hour.  Then 1 person can do 1/24th of the job in 1 hour.  Then 2 people can do 1/12th of the job in 1 hour.  Then 2 people can do the whole job in 12 hours.
John

Egw to Beta kai to Sigma
My calculator said it, I believe it, that settles it
 
RELATED QUESTIONS
if it takes 7 people 15 days to do a job, how long will it take 3 people to do the same... (answered by ankor@dixie-net.com)
It takes 8 hours for 8 people to paint a house. How long will it take 2 people to do the... (answered by edjones)
if it takes 2 people 3 days to do a job how long would it take 5 people to do it... (answered by flame8855,slaborn)
It takes 3 people 15 days to complete a big job, how long will it take 5 people to do the  (answered by alicealc)
It takes 4 hours for 3 people to do a particular job.  How long would it take 2 people to  (answered by josgarithmetic)
Solve the problem. It takes 11 hours for 6 people to paint a house. How long will it take  (answered by gonzo)
It takes 11 hours for 6 people to paint a house. How long will it take 2 people to do the  (answered by Alan3354)
If it takes 2 people to complete a job in 5 hours, how many people will it take to... (answered by richwmiller)
the time it takes to complete a certain job varies inversely to the number of people... (answered by stanbon)