SOLUTION: A takes 6 days less than the time taken by B to finish the piece of work.if A and B together can finish it in 4 days.then find the time taken by B to finish the work by himself?

Algebra.Com
Question 800948: A takes 6 days less than the time taken by B to finish the piece of work.if A and B together can finish it in 4 days.then find the time taken by B to finish the work by himself?
Answer by josgarithmetic(39617)   (Show Source): You can put this solution on YOUR website!
Uniform rates, task-completion problem!

The 1 job being done is, "finish a piece of work". The unit for rate iis jobs per day.

Agent B does the job in some unknown amount of time, call it d.
The rate for agent B is Jobs per Day.
Agent A is faster. Agent A works at the rate of jobs per day. Notice, "6 hours less than... B".

The rate for A and B working at the same time is jobs per day. This is given.

Enough is known to determine "d" for the amount of time that agent B needs to do one job if alone. Their combined rate working together is simply additive.

L.C.D. is like, .




General solution to a quadratic formula:




.
..... You do the rest.

RELATED QUESTIONS

Person A takes 6 days less than the time taken by the person B to finish a piece of work. (answered by stanbon,ikleyn)
A can finish the work in 6 days less than the time taken by B to finish the work.If both... (answered by ankor@dixie-net.com)
A takes 10 days less than the time taken by B to finish an embroidery work. If both A and (answered by Theo,mananth)
A takes 10 days less than the time B to complete a work. If both A and B together can... (answered by ankor@dixie-net.com)
2 men and 5 boys together can a finish a piece of work in 4 days ,while 3 men and h boys... (answered by richwmiller)
A can do a piece of work in 10 days. If A and B work together they can finish it in 6... (answered by Narsinghchauhan8960103366)
A and B together can finish a piece of work in 12 days. it A alone can finish the same... (answered by ankor@dixie-net.com)
When workers A and B work together, they can finish the flooring of a house in 6... (answered by josgarithmetic,stanbon)
Bigyan can do  of a work in 9 days. He calls Amar to finish the remaining work. They work (answered by Collinwilfixyouuprealnice)