SOLUTION: ggreg working 8 hours a day can finish a piece of work in 16 days.how many hours per day must he work to complete it in 12 days
Algebra.Com
Question 795521: ggreg working 8 hours a day can finish a piece of work in 16 days.how many hours per day must he work to complete it in 12 days
Answer by Cromlix(4381) (Show Source): You can put this solution on YOUR website!
Working 8 hours a day to finish work in 16 days
Number hours he must work to complete job in 12 days
= 16/12 * 8 = 10 hours 40 minutes a day.
Hope this helps.
:-)
RELATED QUESTIONS
15 men working 7 hours a day can finish a piece of work in 15 days. How many days will... (answered by ankor@dixie-net.com)
please help me to solve this problem. Thanks.
If 30 laborers working 7 hours a day can... (answered by josmiceli)
If a woman works for 3 1/2 hours per day, she can finish a piece of work in 10 days. How... (answered by Theo)
Working 8 hours a day, 24 men do a piece of work in 15 days. Find how many days it would... (answered by ewatrrr)
12 men working 7 hours a day can finish a job in 6 days. How many more hours a day must 8 (answered by ankor@dixie-net.com)
10 men working 6 hours a day can complete a work in 18 days. How many hours a day must 15 (answered by vksarvepalli)
1.'A' works twice as fast as 'B'. If both of them together take 6 days to complete the... (answered by josmiceli,vvnrichards)
Q1 ) 24 men working at 8 hours per day can do a piece of work in 15 days. In how many... (answered by Alan3354)
15 men working 6 hours a day can do a piece of work in 20 days. how many men working 8... (answered by sadike007)