SOLUTION: Looking for the most efficient method. 20 workers completed a quarter of a job in 8 days. How many more workers does will it take to complete the rest of the job in 5 days?

Algebra.Com
Question 794821: Looking for the most efficient method.
20 workers completed a quarter of a job in 8 days. How many more workers does will it take to complete the rest of the job in 5 days? Each worker works at the same rate.
Answer we have is:
1/4 / 20 = 1/80 - This is the amount of work each worker does per 8 days.
1/80 / 8 = 1/640 - This is the amount of work each worker does per day.
1/640 x 5 = 1/128 - This is the amount of work each worker does per 5 days.
x = the amount of workers
(1/128)x=3/4
x = 96
96 - 20 = 76 additional workers.
This answer is correct but I am trying to find a more efficient method.

Answer by majo89(3)   (Show Source): You can put this solution on YOUR website!
NUM OF MEN*NUM OF DAYS/TOTAL WORK IS CONSTANT.
here 20 men works for 8days to complete 1/4 job.we have to find x where 20+x men are required to complete 3/4 job in 5 days.
20*8/1/4=(20+x)*5/3/4
20*8*4=(20+x)*5*4/3
4*8*3=20+x
x=96-20=76men

RELATED QUESTIONS

Hi 5 workers complete a job in 6 days. After 2 days, 3 workers left. how many more days (answered by Theo)
In doing a project, a group of workers can complete the work in a certain number of days. (answered by scott8148)
A group of 40 workers can finish digging a tunnel in 12 days. how many workers can... (answered by Edwin McCravy)
If a job can be completed by 2 workers in 10 days, then what is the number of workers... (answered by stanbon)
If 4 workers do a job in 6 days..How long will 24 workers will need do the... (answered by josgarithmetic)
12 workers can do a piece of work in 16 days if 12 more workers are added in how many... (answered by Cromlix)
Two workers finished a job in 7.5 days. How long would it take each worker to do the job... (answered by ankor@dixie-net.com)
If it can take 10 days for 5 workers to complete a job, how long will it take 8 workers... (answered by ewatrrr)
60 workers complete a project in 40 days. For the project to be completed in 20 days, how (answered by josgarithmetic)