Question 792019: 4 men and 4 boys can do a piece of work in 3 days while 2 men and 5 boys can finish it in 4 days. How long would it take 1 boy to do it? How long would it take 1 man to do it?
Answer by ankor@dixie-net.com(22740)   (Show Source): You can put this solution on YOUR website!
4 men and 4 boys can do a piece of work in 3 days while 2 men and 5 boys can finish it in 4 days.
:
Find the relationship between a man-day and a boy day
12 man-days + 12 boy-days = 8 man-days + 20 boy days
12 md - 8 md = 20bd - 12 bd
4md = 8bd
divide both sides by 4d
m = 2b (1 man = 2 boys)
:
Find how many man-days required to do the job, replace 2 b with 1 m
3(4 m + 2m) = 18 man days to do the job or 36 boy days to do the job
:
How long would it take 1 boy to do it? 36 days
How long would it take 1 man to do it? 18 days

RELATED QUESTIONS

2 men and 5 boys can do a piece of work in 4 days, while 4 men and 4 boys can do it in 3... (answered by josgarithmetic,MathTherapy,ikleyn)
2 men and 5 boys can do a piece of work in 4 days, while 4 men and 4 boys can do it in 3... (answered by josgarithmetic,ikleyn,MathTherapy)
2 men and 5 boys together can a finish a piece of work in 4 days ,while 3 men and h boys... (answered by richwmiller)
2 men and 5 boys can do piece of work in 4 days , while 4 men and 4 boys can do in 3 day. (answered by Edwin McCravy,oberobic)
2 men can do the same amount of work that 3 boys can do. 4 men and 10 boys can do a piece (answered by josgarithmetic)
1) 2 men and 7 boys can do a piece of work in 4 days. The same work is done by 4 men and... (answered by Edwin McCravy)
If 4 men and 6 boys can finish a piece of work in 24 days, in what time will 8 men and 9... (answered by ankor@dixie-net.com)
If 8 men and 17 boys can do a piece of work in 26 days how many days will it take 4 men... (answered by richwmiller,Vladdroid)
2 men and 4 boys can do a piece of work in 10 days, while 4 men and 5 boys can do it in... (answered by LinnW)