SOLUTION: One crew can seal a parking lot in 15 hours and another in 20 hours. How long will it take to seal the parking lot if the two crews work together?

Algebra.Com
Question 783796: One crew can seal a parking lot in 15 hours and another in 20 hours. How long will it take to seal the parking lot if the two crews work together?
Answer by josgarithmetic(39629)   (Show Source): You can put this solution on YOUR website!
That question in other wording is, what is the combined rate of work for the two crews together?

Their rates would be additive, and you would use unit of job per hour.


Now if you want as HOURS per JOB, then find the reciprocal:
HOURS per JOB
Hours per Job.

RELATED QUESTIONS

One crew can seal a parking lot in 15 hours and another in 20 hours. How long will it... (answered by josgarithmetic)
one crew can seal a parking lot in 12 hours and another can seal it in 16 hours. How long (answered by Boreal)
One crew can seal a parking lot in 8 hours and another in 10 hours. How long will it... (answered by ptaylor)
One crew can seal a parking lot in 8 hours and another in 10 hours. How long will it take (answered by solver91311)
One crew can seal a parking lot in 12 hours and another in 16 hours. How long will it... (answered by richwmiller)
One crew can seal a parking lot in 6 hours and another in 9 hours. How long will it take... (answered by solver91311)
One crew can seal a parking lot in 6 hours and another in 9 hours. How long will it take... (answered by solver91311)
One crew can seal a parking lot in 6 hours and another in 10 hours. How long will it take (answered by ikleyn)
One crew can seal a parking lot in 8 hours and another 12 hours. How long will it take to (answered by Edwin McCravy,Alan3354)