Question 783645: 3 men build a house in 10 days . how long would it take 5 men
Answer by ankor@dixie-net.com(22740) (Show Source): You can put this solution on YOUR website!
3 men build a house in 10 days . how long would it take 5 men
:
Find the number of man-days to complete the house
3 * 10 = 30 man days
:
How long would take 5 men?
Let t = time for 5 men
5t = 30
t = 30/5
t = 6 days for 5 men to do it
RELATED QUESTIONS
If 3 men build a wall in 4 days how long will it take 5... (answered by josmiceli)
If it takes 5 workmen 10 days to build the main shell of a house, how long would you... (answered by stanbon,josmiceli)
if 5 men can build a house in 16 days then how long ll it take just 2 men to build the... (answered by josmiceli)
If 8 men can build a house in 35 days, how many days would it take 14... (answered by TimothyLamb)
It takes 5 men to build a shed in 120 days, how long does it take 3... (answered by Tatiana_Stebko)
If it takes 4 men 20 days to build a house how long would it take 6 men to build the... (answered by stanbon)
it takes 8 men to build a wall in 30 days. How long would it take 10 men to build the... (answered by JulietG)
if 5 men can build a house in 16 days how long will it take just 2 men to build the same... (answered by ankor@dixie-net.com)
If 10 men can build a house in a month. How long does it take for 3,000... (answered by richwmiller)