SOLUTION: Nine men do i piece of work in 28days.how long wil it take 14 men to do it
Algebra.Com
Question 777849: Nine men do i piece of work in 28days.how long wil it take 14 men to do it
Answer by Cromlix(4381) (Show Source): You can put this solution on YOUR website!
9/14 * 28
= 18 days
Hope this helps.
:-)