SOLUTION: A can do a work in 12 days ;B in 6 days and C in 3 days.A and B start working together and after a day,C joins them.The total number of days required to complete the work is (A) 1

Algebra.Com
Question 777735: A can do a work in 12 days ;B in 6 days and C in 3 days.A and B start working together and after a day,C joins them.The total number of days required to complete the work is
(A) 16/7 days (B) 9/7 days (C) 15/7 days (D) 8/7 days

Answer by Edwin McCravy(20056)   (Show Source): You can put this solution on YOUR website!
Jobs done = (rate)×(time), or rather 
 


Let's get the work rates in fraction of a job per day:

A's rate is  of a job per day.
B's rate is  of a job per day.
C's rate is  of a job per day.

A&B's combined rate is 

+ = + =  =  of a job per day.

A&B&C's combined rate is 

++ = ++ =  of a job per day.

When A&B worked for 1 day they did: 

rate×time = ·1 =  of the job.

That left  of the job still undone.

Then C joined them for X days.

So when A&B&C worked for X days they did:

rate×time = X 

and that must equal the remaining  of the job

So the equation is X = 

Multiply both sides by 12

                   28X = 36
                     X = 36/28
                     X = 9/7 days.

Edwin

RELATED QUESTIONS

A,B and C can finish a job in 6 days. If B and C work together, the job will take 9 days; (answered by stanbon,harshachittar)
A can do work in 12 Days,b in 6 days and c in 3 days.A and B start working together and... (answered by josmiceli,lwsshak3)
Working alone, two painters, A and B, can paint a building in 12 and 16 days... (answered by ankor@dixie-net.com)
A and B can do a piece of work in 42 days, B and C in 31 days, and A and C in 20 days.... (answered by ptaylor,Edwin Parker)
A and B together can do a piece of work in 12 days, which B and C together can do in 16... (answered by KMST)
Person A can do a piece of work in 10 days. After he has worked for 2 days, B comes and... (answered by scott8148)
A does 3/10 of a work in 6 days .He then calls in B and they finish the work in 7 days... (answered by ankor@dixie-net.com)
A and B can do a piece of work in 42 days, B and C in 31 days and C and A in 20 days. In... (answered by Edwin McCravy,AnlytcPhil,Edwin Parker)
1.'A' works twice as fast as 'B'. If both of them together take 6 days to complete the... (answered by josmiceli,vvnrichards)