SOLUTION: if it takes 6days for 4men to do a task, how long will it take 2men to do the same task at the same rate?

Algebra.Com
Question 771227: if it takes 6days for 4men to do a task, how long will it take 2men to do the same task at the same rate?
Answer by josgarithmetic(39617)   (Show Source): You can put this solution on YOUR website!
Changing from 4 men to 2 men means the task rate is now half what it was. This means, needing to double the number of days to do the task, so, 2*6 days.

If a more formal solution is necessary for you, say.

RELATED QUESTIONS

Joe takes 30 minutes longer than Mary to do a task. If together they complete the same... (answered by josgarithmetic,ikleyn)
If it takes 3 people 4 hours to complete a task, how long will the same task take for 5... (answered by richwmiller)
bob takes 8 hours to do a task while his son takes 10 hours. How long will it take them... (answered by josgarithmetic)
How long will it take 20 machines to complete a task, given that it takes 12 days for 5... (answered by rfer)
How long will it take 4 workers to complete a task, given that it takes 6 days for 6... (answered by Simnepi)
Suppose that m people can do a task in d days. Assuming that they all work at the same... (answered by mananth)
If it takes 4 hours for one person to perform a task and it takes another person 3 hours... (answered by flame8855)
If it take four men a day's work to complete a specific task, how long will it take... (answered by richwmiller,ewatrrr)
It takes Mary 6 days to complete a task. It takes Mike 8 days to do the same thing.If... (answered by mananth)