SOLUTION: Danielle can complete a project in twelve days and Mackenzie can do the same project in forty-eight days. Danielle worked on the project alone for four days before Mackenzie joined

Algebra.Com
Question 768474: Danielle can complete a project in twelve days and Mackenzie can do the same project in forty-eight days. Danielle worked on the project alone for four days before Mackenzie joined her. How many days did Mackenzie work on the project until it was done?

Found 2 solutions by josgarithmetic, ankor@dixie-net.com:
Answer by josgarithmetic(39623)   (Show Source): You can put this solution on YOUR website!
Danielle's rate: job per day
MacKenzie's rate: job per day
Their combined rate: job per day
Basically r*d=j ----------- r is rate, d is days, j is job quantity

Danielle alone, 4 days.


MacKz joined Danielle, d days, unknown.


The project or job was done in 4+d days.

SOLVE FOR d.

To begin the symbolic solving,



_____________________so actually finished solution.
8 days to finish with MacKenzie.

Answer by ankor@dixie-net.com(22740)   (Show Source): You can put this solution on YOUR website!
Danielle can complete a project in twelve days and Mackenzie can do the same project in forty-eight days.
Danielle worked on the project alone for four days before Mackenzie joined her.
How many days did Mackenzie work on the project until it was done?
:
Let m = no. of days that M worked to complete the job with D
then
(m+4) = no. of days worked by D
;
Let the completed jobe = 1
:
the shared work equation
+ = 1
Clear the denominators, by multiplying by 48, resulting in:
4(m+4) + m = 48
4m + 16 + m = 48
5m = 48 - 16
m = 32/5
m = 6.4 days worked by M
:
:
We can confirm this by finding what fraction of the job each worked
the two fraction should add up to 1, (D worked 10.4 days)
10.4/12 = .867
6.4/48 = .133
---------------
total to: 1.00

RELATED QUESTIONS

Jonathan can complete a project in 15 days and Stephanie can do the same project in 45... (answered by richwmiller)
a girl can build a project on 12 days. a boy can build the same project in 8 days. if... (answered by Edwin McCravy)
alice can complete a project in 20 days and b0b can complete the same project in 30... (answered by Edwin McCravy)
If A and B work on a project, they need 8 1/9 days. A worked alone for 8 days then B... (answered by josgarithmetic,ikleyn)
If 24 staff members can complete a project in 18 days, how many staff members will be... (answered by ewatrrr)
A project can be done by 8 girls in 5 days. 5 boys can do the same project in 6 days. How (answered by Edwin McCravy)
A project can be done by 8 girls in 5 days. 5 boys can do the same project in 6 days. How (answered by emargo19)
25 men can do a project in 20 days . 15 men leave the project after working for some... (answered by josmiceli)